Skip to content
← All systems

Energy

01 · Core systems

Energy is the first constraint on AI. A model can be moved. Racks can be swapped. Megawatts cannot be produced by a software update.

Power is designed before anything else. Every other system follows the connection.

ArchitectureGrid, generation, storage and photovoltaics.

Leonardo da Vinci · Madrid Codices · Biblioteca Nacional de España

Grid connection, combined heat and power, storage and photovoltaics form one stack. The adit joins it as heat: water at 10–12 °C is a source for a heat pump in winter and free cooling in summer, never electricity. Each layer carries its own status and its own date. They are never added into a single number.

Energy

  1. GRID
  2. CHP
  3. STORAGE
  4. PV
  5. LOAD
Energy flow, four layers

SpecificationEnergy

Stand: 08/2026

Grid connection, Blankenburg110 kV / 60 MW1
Combined heat and power~25 MWth2
Combined heat and power, electrical30 MW el3
Transformers, campus2 × 63 MVA4
Grid connection, Quedlinburg1 MW5
Transformer2 MVA6
Photovoltaics450 kWp7
Mine water, thermal capacity1,6 MWth8
Photovoltaics, campus – an area-consistent figureOpen · Engineering
Mine water – abstraction permit, measured temperature and flowOpen · Legal and engineering

01 · EnergyProof

Documents · Technical overview · not yet published.

In Quedlinburg, on-site generation and grid connection are in place. Blankenburg's connection request was filed in March 2026 and is in review.

Control

Metering is continuous and per layer. A layer that is planned reports as planned.

Notes

  1. 1110 kV / 60 MW – SUBMITTED / IN PROCESS (SUBMITTED) · effective 03/2026 · source: Grid connection application · verified 06.08.2026
  2. 2~25 MWth – DESIGN BASIS (DESIGN BASIS) · effective 04/2026 · source: Heat concept · verified 08.08.2026
  3. 330 MW el – DESIGN BASIS (DESIGN BASIS) · effective 07/2026 · source: Technical concept · verified 13.08.2026
  4. 42 × 63 MVA – DESIGN BASIS (DESIGN BASIS) · effective 07/2026 · source: Technical concept · verified 13.08.2026
  5. 51 MW – VERIFIED EXISTING (EXISTING) · effective 08/2026 · source: Project data sheet · verified 06.08.2026
  6. 62 MVA – VERIFIED EXISTING (EXISTING) · effective 08/2026 · source: Site survey · verified 06.08.2026
  7. 7450 kWp – VERIFIED EXISTING (EXISTING) · effective 08/2026 · source: Technical concept · verified 22.08.2026
  8. 81,6 MWth – DESIGN BASIS (CALCULATED) · effective 08/2026 · source: Technical concept · verified 21.08.2026

Document status · Revision 1.0 · Last factual review 22 Aug 2026

Where else to go.

The rest of the site, including the parts a diligence reader wants and the parts the law requires.