Two sites.

Sites

STAND 08/2026

One building being converted, one campus being developed. Both are shown with the figures the engineering runs on, each with its status and the document it came from.

In build

Aerial view of the Quedlinburg building with its official parcel outline
Quedlinburg · official parcel geometry over the aerial
in progress

Quedlinburg

Existing building, converted

A seven-storey building of 1983 on a committed grid connection, becoming an AI data centre. Measured, drawn, filmed, and standing today.

Capacity class1–3 MW class1
Rack envelope, standard positions1842
Existing site connection1 MW3
Revitalisation complete09/20264

In development

Aerial view of the Blankenburg site with its official parcel outline
Blankenburg · official parcel geometry over the aerial
planned

Blankenburg

Campus, built new

The first campus-class site, developed on the holding's own capital and delivered to buyer specification. Its figures follow the engineering, not the other way round.

Grid application110 kV / 60 MW5
Phase 1 IT load50 MW IT6
Heat exportup to 35 MWth7

Capacity, across both.

The two sites answer at different sizes: a megawatt-class hall you can occupy this year, and a campus specified around a buyer. One page plots them on the same ruler.

Notes

  1. 11–3 MW class – DESIGN BASIS (DESIGN BASIS) · effective 08/2026 · source: Project data sheet · verified 06.08.2026
  2. 2184 – DESIGN BASIS (CALCULATED) · effective 08/2026 · source: Technical concept · verified 15.08.2026
  3. 31 MW – VERIFIED EXISTING (EXISTING) · effective 08/2026 · source: Project data sheet · verified 06.08.2026
  4. 409/2026 – LONG-TERM TARGET (TARGET) · effective 08/2026 · source: Project data sheet · verified 09.08.2026
  5. 5110 kV / 60 MW – SUBMITTED / IN PROCESS (SUBMITTED) · effective 03/2026 · source: Grid connection application · verified 06.08.2026
  6. 650 MW IT – DESIGN BASIS (DESIGN BASIS) · effective 06/2026 · source: Project data sheet · verified 06.08.2026
  7. 7up to 35 MWth – DESIGN BASIS (DESIGN BASIS) · effective 06/2026 · source: Heat concept · verified 06.08.2026