Skip to content

A data centre the tourist train comes home to.

Impact

STAND 08/2026

Quedlinburg has been a UNESCO World Heritage site since 1994: 24,000 inhabitants, a thousand years of timber framing, and in the middle of it a black tower that stood empty for years. What it becomes gives the town heat, trade tax and a place that can be walked into.

The Bimmelbahn

The tourist train through the old town ends at a bay on our ground floor.

A tourist train of this type

ILLUSTRATIVE · same type of train, not Quedlinburg's own

The Quedlinburg Bimmelbahn runs from the market square through the old town to the castle hill – a round trip of about 45 minutes, narrated live by the driver, in season. Its bay is on the ground floor of this building. Whoever arrives with it steps off, crosses the corridor and is standing in the exhibition.

A data centre is normally a fence with a camera on it. This one has an address, a door and a timetable.

Departures
operator's published timetable
Duration
approx. 45 minutes
Season
summer season
Exhibition
144 m², directly opposite

The heat

The heat is designed to feed the town's district-heating network.

Electricity that computes becomes heat, all of it: about 21,900 MWh a year at the 3 MW expansion case, which is 2.5 MW of IT load over a full year. Quedlinburg already has a network for it – 9 km of district heating, roughly 43 GWh a year, 99 transfer stations. The heating plant stands on the same street as the Cube, and the nearest 175 homes on that network are 200 metres away.

The network runs past the door

Network operator
Stadtwerke Quedlinburg
Their plant
Süderstadt, 3.5 MW CHP
Address
Klopstockweg 21 – our street
Network
9 km · 43 GWh/yr · 99 stations
Nearest load
175 homes, 200–670 m

A connection is therefore a question of a transfer station and a temperature – not a question of kilometres of new pipe. Those conversations are ahead of us; the network figures come from public sources.

Heat against the town's own network

Quedlinburg district heating, full year

43,000

Waste heat from this building

21,900

Legally required from commissioning (15 %)

3,285

about 7.6 percent of everything the town's network delivers in a year

MWh/yr

0
15,000
30,000
45,000
Network data from Stadtwerke Quedlinburg, building count from the official land register. The dry coolers in the yard remain the guaranteed year-round sink – in summer no heating network takes heat.

Efficiency

The cleanest electricity is the kind never drawn.

A PUE of 1.20 means every kilowatt-hour of compute carries 0.20 kWh for cooling, UPS and losses. The German installed base averages 1.55. At the same compute load that is 0.875 MW less – continuously.

Electricity never drawn
7,665 MWh/yr
Emissions avoided
approx. 2,600 t CO₂/yr

Electricity drawn at 2.50 MW of compute

The same IT load at the German average

33,945

at PUE 1.55 (Bitkom)

This building

26,280

at PUE 1.20 – about 23 percent less

MWh/yr

0
12,000
24,000
36,000
Full load across 8,760 hours. Average from the Bitkom market study.

The law

Germany has the strictest rules in Europe. Here is where this building stands against each.

The Energy Efficiency Act applies to data centres from 300 kW – this one has 3,000. Four requirements, and where the project stands.

01

PUE of at most 1.2

Reached by design: cooling directly in the rack row, free cooling at grade in the yard, short runs. Chillers run roughly 150 hours a year.

met
02

100 % renewable electricity, on a balance-sheet basis, from 2027

450 kWp of photovoltaics are already mounted on facade and roof; the remaining demand is procured as renewable supply.

planned
03

Energy management system, EnEfG §12

Designed to EnEfG §12: metering per circuit and per load, one operations picture, and the reporting path that a certified system is audited against. Certification follows commissioning; it is not a design decision.

in process
04

15 % waste heat reuse from commissioning

The town's district heating network runs past the door. What remains to be settled is the transfer station, the heat pump that lifts 35 °C to network temperature – and the agreement with the network operator.

network in place

The ground

Not one square metre is newly sealed.

Not one square metre is newly sealed.

The building has stood on this plot since 1983. It is converted, not replaced: no excavation, no new ground, no second structure. Of roughly 9,500 m² two buildings are occupied; the cooling needs about 161 m² of the open ground.

Aerial photograph of the plot: the Cube and the open ground

AERIAL · the Cube and the open ground that stays open

0
2,500
5,000
7,500
9,497
The Cube
622
Neighbouring building
274
open ground
8,601

Areas from the land register, drawn to scale.

What the town gets

The building runs unmanned in normal operation. The benefit to Quedlinburg is not in the payroll, and we say so before the first town meeting rather than after it.

Heat

Up to 3,285 MWh a year could go into the existing district heating network – arithmetically about 7.6 percent of what the town's network delivers in a year.

Trade tax and local trades

Trade tax at this location, and local trades throughout the construction period.

A place instead of a vacancy

A building with no use gets one – without a new shed appearing at the edge of town. With 144 m² of exhibition, opposite the Bimmelbahn's bay.

Where else to go.

The rest of the site, including the parts a diligence reader wants and the parts the law requires.