Quedlinburg
EXISTING ENERGY ASSET · AI CONVERSION · KLOPSTOCKWEG 10A, QUEDLINBURG
1 MW existing site connection, 2 MVA on site, 2.33 MWh stored. The energy is already here.
Book a site visitWhat runs, what is being designed, what is open.
Twelve lines, three states, one date. Nothing here is summed.
- complete
Building
In use
- complete
Grid connection
1 MW, metered
- complete
Transformer
2 MVA on site
- complete
Storage
2.33 MWh installed
- complete
Photovoltaics
450 kW on the façade
- complete
Antenna hosting
Two carriers, under contract
- in progress
Low-voltage distribution
Going in
- in progress
AI feed
1.5 MW, design basis
- in progress
Cooling
In-row air, design basis
- planned
Fibre
Contractual status under verification
- planned
Permitting
Not started
- planned
Customer
Open
Stand: 08/2026
Four layers, four separate statuses.
- completeExisting assetBuilding, grid, storage, PV — existing
- completeEnergy systemGeneration, storage, antenna hosting
- in progressBlackKub · AI compute1–3 MW class, in development
- plannedAI FactoryExperience centre, training, community
Stand: 08/2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
- STATUS
- MEASURED
- EFFECTIVE
- 06/2017
- SOURCE
- Structural drawing
- VERIFIED
- 04.08.2026
- STATUS
- MEASURED
- EFFECTIVE
- 06/2017
- SOURCE
- Structural drawing
- VERIFIED
- 04.08.2026
- STATUS
- MEASURED
- EFFECTIVE
- 06/2017
- SOURCE
- Structural drawing
- VERIFIED
- 04.08.2026
- STATUS
- MEASURED
- EFFECTIVE
- 06/2017
- SOURCE
- Structural drawing
- VERIFIED
- 04.08.2026
- STATUS
- SIGNED REPORT
- EFFECTIVE
- 01/2023
- SOURCE
- Structural drawing
- VERIFIED
- 31.07.2026
- STATUS
- CALCULATED
- EFFECTIVE
- 08/2026
- SOURCE
- Technical concept
- VERIFIED
- 15.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
- STATUS
- DESIGN BASIS
- EFFECTIVE
- 08/2026
- SOURCE
- Letter of intent, 08/2026
- VERIFIED
- 15.08.2026
- STATUS
- SUBMITTED
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 09.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Site survey
- VERIFIED
- 06.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Technical concept
- VERIFIED
- 06.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 09.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Technical concept
- VERIFIED
- 06.08.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
- STATUS
- MEASURED
- EFFECTIVE
- 08/2026
- SOURCE
- Site survey
- VERIFIED
- 07.08.2026
- STATUS
- OFFICIAL DATA
- EFFECTIVE
- 07/2026
- SOURCE
- Cadastral data
- VERIFIED
- 29.07.2026
- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Cadastral data
- VERIFIED
- 29.07.2026
- STATUS
- TARGET
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 09.08.2026

Two companies, two roles.
Black Vault is developing the proposed AI and compute layer in cooperation with the existing I-Kubus energy infrastructure.

- complete
I-Kubus GmbH
The existing building and its energy infrastructure
- in progress
Black Vault
The proposed AI and compute layer, and the commercial route to it
Whose building this is.
The tower was bought and converted long before anyone here was talking about compute. That is worth saying first, on his page.

Lars Gottschligg
Black Vault's main partner in Germany
Managing Director, I-Kubus GmbH
Bought the tower more than ten years ago and turned it into the I-Kubus: grid connection, storage, photovoltaic façade. Everything running in the building today runs because of that decision.
From Lost Place into Future Place. Recognising the resources, and using what the energy transition makes possible, innovatively and sensibly. For an economic and environmentally sound future for new energy sites: my commitment, and everything I have.
From the founder
Anna, on the roof.
Director, 12 Elements Ltd
- €100 m–€1 bn
- infrastructure and technology mandates
- Oxford programme, AI Governance & Public Policy
- Davos, every year since 2023
At the Quedlinburg site.
Five things that exist. Photographed.
One picture, one figure from the register.

BESTAND · 08/2026 · the compact substation, doors open 1 MW
EXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
The building's grid connection is metered and live.

BESTAND · 08/2026 · busbars and the incoming feed, L1 L2 L3 2 MVA
EXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Site survey
- VERIFIED
- 06.08.2026
The transformer and the low-voltage distribution it feeds.

BESTAND · the façade from inside, DC cabling on the substructure 450 kW
EXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Technical concept
- VERIFIED
- 06.08.2026
Generation on the building's skin, not on a field beside it.

BESTAND · the carriers' antennas at the roof edge Vodafone · Telefónica
EXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
Two carriers host equipment here, under running contracts.
AS IT STANDSCONCEPTBESTAND · a floor as it stands, end to end 4,431 m²
EXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
Seven structurally sound, empty floors make this a fit-out, not a build.
Conversion of the existing structures.
A prefabricated DDR office tower that stood empty for thirty years, converted twice: first into an energy building, now into an energy and compute node.
BeforeTodayBESTAND · the primary structural frame was retained and repurposed.


≈ 1983
VEB Mertik
VGB system, catalogue B 8619 PKI: precast columns, beams, and hollow-core planks—catalogued parts that make the 40-year-old structure load-checkable.
1990s
Empty
Vacant from the early nineties. Structure intact, façade intact, nothing removed.
2023
E-Kubus
The E-Kubus concept: façade PV, ground-floor battery storage and charging at grade. Structurally verified January 2023.
2025–2026
Energy conversion
Energy conversion and revitalisation. I-Kubus is carved out of SSC hydrovent AG and acquired by I-Kubus GmbH on 17.04.2025.
now
Platform node
Grid, storage, PV and antenna hosting are running. Compute is planned for the floors above.
The existing energy asset.
The list below is the energy infrastructure existing in the building, operated by I-Kubus. The picture beside it is the same building as it stands and as it is intended to look.
AS IT STANDSCONCEPTBESTAND 06/2026 ↔ CONCEPT · the same corner




The battery floor carries the machine floors.
Batteries below, the machine above. Here scrolling is climbing: the section holds still and the floor changes.
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
CONCEPT
BESTAND
BESTAND
AS IT STANDSCONCEPTWhat is here. What we install. What you bring.
The same building, read as a chain. The line style is the answer, so nothing has to be taken on trust from a sentence.
- Existing
- Our scope, to be installed
- Customer configuration
- 01Grid connection1 MW existing site connection, metered, through the compact substation outside.
- 02Transformer2 MVA on site, stepping the connection down to low voltage.
- 03Low-voltage distributionThe main distribution boards, going in now: busbars fitted, cables run.
- 04Dedicated AI feedA separate new transformer for the AI stage, at the 1.5 MW development basis.
- 05UPS and PDUConditioning and distribution to the floor. Topology follows the availability class a customer specifies.
- 06Data floorTwo upper floors fitted out: containment, cable management, fire compartmentation.
- 07In-row coolingAir with hot-aisle containment, at the 13.6 kW/rack the layout is designed around.
- 08Racks and hardwareYours. Accelerator, density and redundancy are the customer's design, and they set what the floor above has to become.
Every rack count needs a density beside it.
184 positions at 13.6 kW
Counted from our two-floor rack layout at 2.5 MW IT in the 3 MW expansion case, below the ~15 kW ceiling-air-with-containment limit, hence in-row cooling.
Higher density, by design
Past that ceiling the building takes liquid to the rack, and the figure follows the accelerator a customer specifies. We compute it against your hardware.
One megawatt of site connection. The compute comes next.
Steps, not a sum.
01 · Existing site connection
1 MW
completeEXISTING- STATUS
- EXISTING
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 06.08.2026
Through the existing 2 MVA transformer.
02 · Dedicated AI connection
1.5 MW
in progressDESIGN BASIS- STATUS
- DESIGN BASIS
- EFFECTIVE
- 08/2026
- SOURCE
- Letter of intent, 08/2026
- VERIFIED
- 15.08.2026
Current engineering basis, on a separate new transformer. Subject to grid confirmation.
03 · Expansion case
3 MW
plannedSUBMITTED- STATUS
- SUBMITTED
- EFFECTIVE
- 08/2026
- SOURCE
- Project data sheet
- VERIFIED
- 09.08.2026
Applied for with the grid operator. Not granted.
The full rack envelope and the design density belong to the far end of this sequence, not to today's connection.
The programmeThis building is the first step, not the plan.
The Cube is Black Vault's smallest and first standing project, within a 2 GW European build-out by 2035 and a five-year plan for 100 small datacenters. This building is the block at the center.
100
datacenters in Germany and Europe, one company each
Two under way today · Target · Stand 08/2026
Come and read the plates yourself.
Everything on this page marked as existing can be stood in front of. We assemble visits in groups; tell us what you need to see and we will say what is open on the day.
Klopstockweg 10a, Quedlinburg. Ninety minutes covers all of it. Bring whoever has to sign.
- completeThe building, all seven floors
- completeThe compact substation, doors open
- completeThe transformer and the low-voltage distribution
- completeThe battery room
- completeThe photovoltaic façade, inside and out
- completeThe roof, its antennas and its plant
Document status · Revision 01 · Updated 07 Aug 2026
Technical owner: Engineering · Data cut-off: 07.08.2026






